Sports facility · Bourg-la-Reine (92)
Construction of the Bas-Coquarts sports complex in Bourg-la-Reine (92)
Scope of services: French project phase codes
- APS: Outline design
- AVP: Preliminary design
- PRO/DCE: Detailed design and tender documentation
- ACT: Assistance with tendering and contract award
- VISA: Review of contractors’ execution drawings for conformity with the design
- DET: Supervision and administration of construction contracts
- AOR: Assistance with acceptance, handover and defects close-out
- Client
- Mairie de Bourg-la-Reine, 6 boulevard Carnot, 92340 Bourg-la-Reine
- Design team
- HALL EXPO-GL Events, NP2F, BOST ingénierie, ALTO fluides, ALTIA, AVR, Deloménie, BGC
- Area
- 3,600 m²; external areas: 1,860 m²
- Project dates
- Design started in 2021; construction completed in 2024
- Construction cost
- €8.5 million; civil infrastructure and utilities: €544,000
- Scope of services
- APS, AVP, PRO/DCE, ACT, VISA, DET, AOR.
Key project features
- Bulk earthworks.
- Stormwater treatment and attenuation basin.
- Roads and external works.
- Utility networks and external lighting.